Mt Annan leisure centre’s turn for major makeover

Photo of author

 

Camden pool is back in business after major repairs, and now is the turn of Mt Annan leisure centre.

Work will start on March 1 with repairs to the pool hall roof the main goal.

It is expected that by August the makeover will be complete and the popular leisure centre will be as good as new again.

The project will be completed in stages.

Stage One works will mean the closure of the leisure and program pool; the 25 metre pool will be closed to allow the second stage of work.

Mayor of Camden, Cr Therese Fedeli, said council secured more than $1.7 million in funding as part of the third round of the Australian Government’s Local Roads and Community Infrastructure Program to undertake this project.

“We were so thrilled to have reopened Camden War Memorial Pool earlier this year, after it underwent extensive repair work as a result of damage caused by last year’s flooding events,” Cr Fedeli said.

“Work included the emptying, repairing and refilling of the 50-metre and leisure pools; repairs to the plant room roof, roof framework and cavity; the replacement of solar heating roof lines and pool heat pumps; and much more.

“This facility has had its season extended to 30 April 2023, so there’s still plenty of time to enjoy it.

“We’re constantly looking at improving our area and the fantastic facilities within it, so now it’s Mt Annan Leisure Centre’s turn to have a face-lift,’’ Cr Fedeli said.

“We know Mount Annan Leisure Centre is a widely loved and used facility by many of our residents and visitors, so I’m looking forward to having these works done over the next few months so everyone’s experience at the facility is all the better for it.”

Work on Mt Annan leisure centre will include:

The replacement of all box gutters in the pool hall and deteriorated roof flashings and fixings;

Remedial work to structural steel columns, steel wall framing, acoustic ceiling panels and steel frames for the external bi-fold doors.

For more information on this project visit https://www.camden.nsw.gov.au/major-developments/mount-annan-leisure-centre-malc-roof-restoration-works

1 thought on “Mt Annan leisure centre’s turn for major makeover”

  1. Mount Annan Leisure Centre is a great facility BUT why is the water slide never working my grandchildren so want to use the slide

    Reply

Leave a Comment